    The client says what information it needs. The BEP says how, by whom and when it will be produced.

    The problem

    “I want it in BIM” is not a requirement.

    If nobody writes down what information is needed, each team understands something different and the delivery is useless for what the client needed.

    01 Too much geometry
    02 Too little data
    03 A format nobody opens
    What was missing
    WhatWhat forWhenWhoHow
    The solution Written requirements and a plan that answers them
    Information requirements

    From strategy to data.

    Requirements cascade down: from what the organisation needs to know about its assets to what each appointment must deliver.

    Four acronyms, one order OIRthe organisation PIRthe project AIRthe asset EIReach appointment → PIM→ AIM
    The E in EIR Exchange formerly “Employer's”: now one per appointment
    The parties

    Who asks and who answers.

    The appointing party appoints a lead appointed party, which coordinates its appointed parties. Together they form the delivery team.

    Project team APPOINTING PARTY LEAD APPOINTED PARTY Appointed party Appointed party Appointed party task teams EIR + appointment delivery team
    BIM execution plan

    The BEP answers the EIR.

    The EIR says what information the client wants. The BEP explains how the team will produce it, with what resources and under which standards.

    Question and answer EIRBEP What?When?Format?Rules?
    Two versions Pre-appointmentwith the tender response Post-appointmentafter the appointment
    What it contains

    Seven minimum sections.

    The standard sets what the BEP submitted with the tender response must include. The rest is form: neither page count nor logos make it better.

    1Peopleinformation management
    2Delivery strategyhow the EIR is met
    3Federationhow the model is split
    4Responsibilitymatrix
    5Methodsof production
    6Standardnames, units, EPSG:25830
    7Software, hardware and IT infrastructureprograms, versions and formats of each team
    Responsibility matrix

    Who produces what.

    Each deliverable, crossed with the team that produces it. In the tender response it is high level; after the appointment, it is detailed down to the information container.

    Deliverable × team ARCSTRMEPSUR Arch. modelStr. modelFederatedSurvey
    Legend
    ProducesContributesCoordinates
    a single owner per row
    Delivery plans

    Each team, its own plan.

    Each task team writes its TIDP: which information containers it delivers and when. The lead appointed party combines them into a single MIDP.

    Three TIDPs → one MIDP TIDP ARCTIDP STRTIDP MEPMIDP milestone 1milestone 2
    Information delivery milestones

    Information arrives when a decision is due.

    Milestones are set where the client needs data to make a decision, not when the team finishes modelling.

    Decision points FeasibilityOutlineTechnicalBuildHandover proceed?permit?tender?accept?operate? each diamond = an exchange with its level of information need
    Level of information need

    No more, no less.

    For each milestone and purpose, you set how much geometry, which data and which documents. Excess costs as much as gaps.

    Geometry Detail, dimensionality, location
    Data Properties and values
    Documentation Data sheets, certificates, manuals
    Defined by
    PurposeMilestoneWho asksObject
    Common data environment

    Four states per container.

    Every file moves from work in progress to shared, published and archived. Each step has a check and someone who signs it off.

    States and transitions IN PROGRESS SHARED PUBLISHED ARCHIVED checkreviewauthoriseacceptrecord WIPSHAREDPUBLISHEDARCHIVED
    Maintenance

    Updated, not filed away.

    The BEP is offered, confirmed at appointment and revised whenever something that affects the information changes: a stage, a team, a program.

    Life cycle OFFER CONFIRM APPLY REVISE
    What forces a revision
    Change of stageNew appointed partyNew program or versionChange to the EIRLesson learned
    How to recognise one

    Specific, named and checkable.

    A BEP copied from another project shows: it speaks in generalities. A useful one answers each requirement with a person, a date and a way to check it.

    Filler BEP
    • “BIM software will be used”
    • “The team will coordinate the models”
    • “The standard will be followed”
    Useful BEP
    • Program, version and format per team
    • Weekly federation, named person in charge
    • IFC4 validated against the EIR’s IDS
    ISO 19650

    Six parts, one language.

    Concepts, delivery phase, operational phase, exchange, security, and health and safety. In Spain they are published as UNE-EN ISO 19650.

    Parts and ISO publication year 2018202020222025 215346 deliveryconceptssecurityoperationexchangehealth & safety
    Revision under wayParts 1 and 2the new part 2 absorbs part 3 · draft back to ballot
    Spanish committeeUNE CTN 332mirror of ISO/TC 59/SC 13 and CEN/TC 442
    ISO 19650-2

    Eight activities, two BEPs.

    Part 2 organises each appointment into eight activities. The BEP appears in the tender response and is confirmed at appointment.

    Information management process 12345678 Assessmentand needInvitationto tenderResponsepre-app. BEPAppointmentBEP · MIDPMobilisationCollaborativeproductionModeldeliveryClose-out client: 1-2delivery team: 3-7both: 8
    Where it comes from

    Born British, made ISO.

    The BEP and the EIR come from UK standards and moved into ISO in 2018. The revision under way could change their names.

    Timeline 20072013201820192027? BS 1192naming, CDEPAS 1192-2EIR = Employer'sISO 19650-1/2EIR = ExchangeUNE-EN ISOSpanish editionrevisionnew name?
    UK National Annex

    A name that explains itself.

    The UK annex proposes field-based names and a status code for every file. It is the model many CDEs and tender documents copy.

    Seven fields separated by hyphens HSP ARQ ZZ 01 M3 A 0001 ------ projectoriginatorvolumeleveltyperolenumber M3 = 3D model · A = architecture · ZZ = all volumes
    Status codes
    S0 in progressS1 coordinationS2 informationS3 reviewS4 stage approvalA1 authorisedB1 with commentsCR final record
    Example · Spain

    The Plan BIM sets dates.

    The Spanish State requires a BIM level according to contract value. From October 2025, Intermediate level for works above the EU threshold.

    Required level · Spanish central government contracts Apr 2024Oct 2025Oct 2027Apr 2030 ≥ threshold€5 404 000€2M – thresh. INITIALINTERMEDIATEADVANCEDINTEGRATEDINITIAL*INITIALINTERMEDIATEADVANCED * recommended · works threshold in force since 1/1/2026
    Approved27/06/2023Orden PCM/818/2023
    RequiresIFC + BCFand the UNE-EN ISO 19650 series
    Overseen byCIBIMset up by RD 1515/2018
    Beyond ISO

    Other guides, same idea.

    The United States, Singapore and Peru have their own BEP guides. Names and order change; the question-and-answer structure stays.

    Penn State · USA5stepsguide v3.0 from 2021, by BIM uses
    NBIMS-US V4 · USA3momentsrequest, proposal and full plan
    BCA · Singapore2013BIM Essential Guide for BEP
    Plan BIM Perú2021national guide based on NTP-ISO 19650, updated in 2023
    Authoring software

    Every decision ends up as a setting.

    Template, properties, names, coordinates and export: what the BEP decides is configured once in each program and shared with the team.

    From the document to the program Information standardLevel of informationNaming conventionCoordinatesDelivery formats project templateproperties · IDSviews, sheets, filesSurvey PointIFC export setup
    ArchicadImports an IDSand creates its properties and classifications
    RevitTemplate + shared parametersand a saved IFC export setup
    Drafting the BEP

    From template to data.

    Almost all are written in text templates and spreadsheets. Some platforms turn them into data linked to the checks.

    TextOfficial templatesUK BIM Framework · Euskadi · Peru
    TablesSpreadsheetmatrix, TIDP and MIDP
    DataPlannerlyBEP, LOIN and verification
    The difference
    Document→Table→Checkable requirement
    CDE platforms

    The platform enforces the BEP.

    A well-configured CDE sets aside non-compliant names, assigns status codes and blocks publishing without approval.

    Autodesk Docs
    Naming validatorHolding areaS0–S7 · A · B · CRApproval in 1–6 steps
    Bentley BCDE Project work in progress, shared, published and archived states; naming checks
    CertificationBSI KitemarkISO 19650 software, since March 2021
    Before choosingThe BEP rulesthe platform is configured from it
    Approval workflow

    From S0 to A1, signed off.

    Every status change is a workflow: who reviews, who approves and which folder the file moves to. The BEP says it; the platform runs it.

    One file, four sign-offs S0S1S3 → S4A1 authortask team leaderchecksinformation managerreviewsappointing partyauthorises, accepts IN PROGRESSSHAREDPUBLISHED
    Delivery formats

    Open formats, in the contract.

    The EIR sets the format for each deliverable and the BEP says which program and settings produce it. Spain’s Plan BIM requires IFC and BCF.

    IFCThe modelISO 16739-1:2024 (IFC 4.3)
    BCFThe issuesfile or API
    IDSThe requirements1.0, June 2024
    COBieData for maintenancesheets and tables for operation
    And alsoNative + PDFif the EIR asks for them, with version
    IDS · buildingSMART

    The machine-readable EIR.

    With IDS, the part of the EIR that asks for data is written in XML that any checker reads the same way. The BEP says who runs it and when.

    In the EIR “All doors shall carry their fire rating.”
    In the IDS IfcDoor → Pset_DoorCommon
    FireRating required
    From text to check
    EIR as text→IDS→Delivered IFC→Report and BCF
    Quality control

    Five questions per delivery.

    Before sharing or publishing, every container answers: what it is called, what state it is in, what data it carries, whether it coordinates and whether it is in the right place.

    01 · NameFollows the convention
    02 · StatusCode and revision
    03 · DataPasses the IDS
    04 · CoordinationNo open clashes
    05 · PositionEPSG:25830and control point
    Tools

    Each check, its tool.

    The CDE polices the names; an IDS, the data; a federated viewer, the coordination. The BEP says which one is used and who signs the report.

    IfcTesterFree IDSHTML or BCF report
    SolibriRule 244IDS validation
    BIMcollabNexus + ZoomIDS and BCF issues
    Autodesk DocsNaming validator
    IFCValidation ServicebuildingSMART: making sure the IFC is IFC
    Assessing the BEP

    The BEP itself is reviewed too.

    Before the appointment, the client scores the pre-appointment BEP: whether it answers every requirement and whether the team has the real capacity to deliver it.

    Assessment sheet Answers every EIRNamed peopleCapability, capacityMobilisation, testsInformation risks
    Warning signMobilisation without testsnobody has tried the workflow before starting
    In summary

    Four rules.

    01Ask in writingone EIR per appointment
    02Answer point by pointthe BEP, with names
    03Plan the deliveriesTIDP, MIDP and milestones
    04Check each oneCDE, IDS and viewer